Day 15 - September 16th

There seemed to be a lot of work going on today, I'm just not sure what all of it was! The smoke/fire detection system got tested, the setup and testing of the Visual Image Generator continued and the installation of the pedestals for the visual projectors got underway.

I was busy restoring a disk on another simulator, so I missed out on some of today activities. I saw that there's a terminal connected to the Motion Cabinet, so I suppose the EMM was getting set up. The accessway gate got installed and adjusted and I think some testing was being done on what we call the linkage, which controls input/output communication between the equipment and the computers.