Day 19 - September 20th

Today SimX completed the cabling to the projectors and the CAE Visual Specialist mounted the projection lenses and worked on the projector setup. The visual mirror setup appears to be complete and the mirror is stretched smooth with the vacuum pump running.

The non-skid flooring was installed, but the carpet installation was delayed due to a shortage of a special sound-deadening underlayment.

Itegration and QTG testing continues.