Also today the visual mirror vacuum pump was started and the mirror was being stretched and adjusted. Visual projector power was applied and the projector setup got underway.
SimX packed their tools and are getting ready to leave since all the heavy rigging and installation jobs are nearly complete.
Inserting the base of the maintenance jack into the lower bracket
The upper bushing is rotated allowing the jack to be extended into the upper bracket and take the weight of the simulator off of the motion jack
A strap is installed at the motion jack center-of-gravity so the jack will balance when lifted
After finding the "sweet spot" where the minimum amount of force is acting on the upper pin, the pin can be removed freeing the upper end of the motion jack
Oops! Ran outta gas after removing the motion jack
Adjustments being made to accessway ramp 'down' switches
One power cable to a visual projector was found to have a broken wire and had to be replaced
CAE visual specialist, Henry Ng, arrived today
The upper bushing is rotated allowing the jack to be extended into the upper bracket and take the weight of the simulator off of the motion jack
A strap is installed at the motion jack center-of-gravity so the jack will balance when lifted
After finding the "sweet spot" where the minimum amount of force is acting on the upper pin, the pin can be removed freeing the upper end of the motion jack
Oops! Ran outta gas after removing the motion jack
Adjustments being made to accessway ramp 'down' switches
One power cable to a visual projector was found to have a broken wire and had to be replaced
CAE visual specialist, Henry Ng, arrived today